Case study · Energy – electrical equipment
Connected circuit breaker: 9 functional tests on a 20 m² line, delivered in 6 months
20 s
takt time per product
−30%
floor space vs. the previous robotic solution
80%
of the machine is reusable
6 months
project lead time
Background
A European leader in electrical equipment is industrializing a new connected circuit breaker in France. Each product undergoes nine functional tests before packaging, at a rate of one part every 20 seconds, on two 8-hour shifts.
Challenges
Chain nine tests together without multiplying robots and conveyors, fit within a small footprint, and launch series production in 2025 on a tight schedule.
The OSE Solution
A PROLYNK line: 15 autonomous mobile robots carry each product from station to station, between manual workstations, test benches, and packaging. An automatic battery changer keeps the line running continuously.